PROJECT MILESTONES

Published by Grand Reve

Screenshot 2022 02 16 103125 at Grand Reve

CONSTRUCTION
UPDATE VIDEO

▲ July 2023

Our builder Dasco has progressed significantly with construction activity culminating in the anticipation of the ground floor slab pour by late July 2023. We will see notable activity onsite over the coming months as further floor slabs are poured with the likely topping out on track for late 2023.

Screenshot 2022 02 16 103125 at Grand Reve

CONSTRUCTION
UPDATE VIDEO

▲ September 2022

Watch our latest construction update video from Dasco here.

Screenshot 2022 02 16 103125 at Grand Reve

CONSTRUCTION
UPDATE

▲ August 2022

Construction is well advanced with the excavation nearing completion. The erection of the tower crane will be the next major milestone – expected to be installed in November. The real activity will then take place, culminating in the buildings topping out by late 2023. Practical Completion is slated for around early-to-mid 2024 and the anticipated move-in-date will be soon after.

01 northwest at Grand Reve
Site update, August 2022 — looking north-west
02 south at Grand Reve
Site update, August 2022 — looking south
03 southeast at Grand Reve
Site update, August 2022 — looking south-east
04 southwest at Grand Reve
Site update, August 2022 — looking south-west
Screenshot 2022 02 16 103125 at Grand Reve

CONSTRUCTION
HAS COMMENCED

▲ January 2022

Early on-site site works are well underway with demolition now complete. The next construction phase will see Sydney Water commence the redirection of the sewage and drainage which is expected in the month of February. Once complete, the early basement excavation works will begin for the digging of the car parking. Our anticipated completion is scheduled for early-to-mid 2024.

Photo 6553993 DJI 393 jpg 4181567 0 202221163816 photo original at Grand Reve
Photo 6554031 DJI 431 jpg 4278641 0 202221165628 photo original at Grand Reve
Screenshot 2022 02 16 103125 at Grand Reve

DEMOLITION HAS
BEEN COMPLETED

▲December 2021

Published by Grand Reve

In early December 2021, the first major milestone was achieved with the demolition of the existing homes on site. All were completely removed before Christmas, with the land flattened to make way for the next phase of early works – the redirection of sewer and water by Sydney Water.

Play Video
DJI 0086 1 at Grand Reve

Visit our
display suite
open daily
10am - 4pm

or book a private appointment

Scroll to Top